Folkestone & Hythe District Council says Folkestone – A Brighter Future is now “80% complete”. It’s a neat little figure, polished until it shines: the sort of percentage meant to suggest the builders are on the home straight, the snagging list is down to a few odds and sods and somebody ought to start looking for the ribbon and oversized scissors.
Take off the rose-tinted spectacles and the picture isn’t nearly so rosy. The foundations for the Guildhall Street footbridge are still being built, the bridge itself isn’t due to be installed until September, granite paving and benches are still going into Bouverie Square, and the council still hasn’t published one firm, consistent date for the whole scheme to be finished.
The main construction works began on 7 April 2025. The entire programme had been due to finish on 31 March 2025. In other words, the diggers turned up a week after the original finishing line had already been crossed, the bunting taken down and the stopwatch put back in the drawer.